Display subtasks in a backlog

How could I configure GreenHopper to display subtasks in the backlog/sprint and to be able to edit estimates?

Is it possilbe to calculate parent issue estimate (story points) based on subtasks estimates?

1 answer

1 accepted

The subtasks do not display in the backlog directly, they are shown in the Sub-Tasks tab on the detail view that appears when you click on the issue. You can see what the tab looks like in a screenshot from the release notes.

You can enter the estimate for the sub tasks when you create it from the sub-tasks tab.

There is currently no way to roll up a story point estimate to the parent issue. For more discussion about estimation you might like to check out an answers post on the topic.

Thanks,
Shaun

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Jan 29, 2019 in Jira Software

Transforming Jira Software projects for general project management purposes

...It's true that there are projects in Jira; but they are merely a way to cut off issues, to tell them apart from other sections of work and to apply rules that are specific to that team (the schemes)....

176 views 0 6
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you