Changing the order of unstarted Sprints

KevinB August 15, 2013

In Plan, we organized by creating several future Sprints. We tried to move one to the top of the list.

It seems like the top one is the ONLY one that has the start controls?

How do you move around Sprints?

Bonus points for what the control with the two horizontal lines at bottom of each sprint does.

Thanks

5 answers

1 accepted

0 votes
Answer accepted
Ronny Katzenberger August 15, 2013
Hi Kevin, there is no way to reorder these future sprints. I would recommend renaming those sprints and "reorder" them that way. To move the assigned stories around, I would select all the stories you want to move and then right-click and "Send to SPRINTNAME" The double horizontal line are your grabber to pull down the sprint scope. Meaning that you can easily add stories from below this sprint into the sprint (pull down) or move stories out of the sprint and into the next sprint (pull up). Hope this helps. Best, Ronny
Martin
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
November 30, 2014

The ability to reorder or reorganise sprints was shipped in JIRA Agile 6.6.11, please see the release notes at https://confluence.atlassian.com/display/AGILE/JIRA+Agile+6.6.11+Release+Notes or documentation at https://confluence.atlassian.com/display/AGILE/Editing+or+Reordering+a+Sprint#EditingorReorderingaSprint-Reorderingasprint The feature was tracked in issue https://jira.atlassian.com/browse/GHS-6131 and was resolved on 03/Nov/14.

3 votes
RicardoA
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 16, 2013

Hi Ronny

As you can see in the official documentation:

Enabling Labs features

To switch 'Labs' on:

Log in as a user with the 'JIRA Administrators' global permission.

Select JIRA Administration from the top bar, then select Add-ons > GreenHopper.

OR, if you are using JIRA 6.0 or later, click the 'cog' icon in the top bar, select Add-ons, then scroll down the page to the GreenHopper section.

Under GreenHopper Labs, select the features that are of interest to you:

Parallel Sprints

Analytics

Parallel Sprints

Turn on Parallel Sprints to enable multiple active, parallel sprints. For example, if you have two teams working from the same backlog, each team can now work on their own sprint.

Please note the following caveats with this simple approach:

The Velocity Chart will not show the velocity per team.

The current implementation assumes that the teams perform estimation identically, which is unlikely in practice.

Please note that this feature is still undergoing development and may change from its current implementation.

You can have multiple sprints, but you have to enable labs.
See more informations here:
Best Regards,
Ricardo Carracedo.
0 votes
Martin
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
November 30, 2014
The ability to reorder or reorganise sprints was shipped in JIRA Agile 6.6.11, please see the release notes at
or documentation at
The feature was tracked in issue https://jira.atlassian.com/browse/GHS-6131 and was resolved on 03/Nov/14.
0 votes
Mart Sõmermaa September 22, 2014

This will be fixed soon, see https://jira.atlassian.com/browse/GHS-6131

0 votes
Neil Swonger January 28, 2014

So you cannot change the order that sprints are displayed?