Add a Screen to the Create Window

Frank Lohfeld March 22, 2019

Hallo Jira Experts.

i want use two different Screens for the Standard View of an Task i want use the screen "CS: Screen View" and for the Create Screen i want use the Screen "CS: Screen Edit"

How can i do this? For all other transitions it is no problem. i can add the screen in workflow. But for create it doesn't worked

Create Screen

Unbenannt2.PNG

 

StandardView:


Unbenannt.PNG

1 answer

1 accepted

1 vote
Answer accepted
Mikael Sandberg
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
March 22, 2019

You need to go and edit the screen scheme that the project is using, from here you define what screen is used for viewing, editing and creating. Go to Administration > Issues > Screens > Screens Scheme. Have a look at Editing a screen scheme's details for more information.

Frank Lohfeld March 22, 2019

boah is that concealed.