How is the priority score calculated?

Hi team!

We have been using Jira Product Discovery over the last few weeks and are really enjoying it so far. I would like to get some more understanding of how the priority scores are calculated? Both fields (Effort and Key Results Impact) have a score between 0-100 with the options 0, 25, 50, 75 and 100 able to be selected with a weighting of 50% each. The weighted score then has a calculated score of 99, 73, 74 etc which is not what we expected. Our expectation is that the fields would be added and then divided by two. Can you please provide some insight into how the weighted scores are calculated?

 

Thanks, 
Jessie

2 comments

Hi @Jessie Renton ! 

You're right, the weighted score formula is both automagical and obscure, and we're not doing a great job at explaining it in the app. 

Basically, what the formula does is to consider your input and how important you rate it (using weight). Then based on that it gives each idea a number between 0 and 100, based on that input (where 0 is the least important idea and 100 the most important)

 Now here are a few examples to explain how it works (Video, 5min)

Now to make it something I can explain in 1 minute instead cheeky

Like Jessie Renton likes this

Oh by the way @Jessie Renton we got your bug report re: deleting field options. We currently have an issue that's automatically closing the right sidebar unexpectedly - this is causing that, we have a fix in the works. 

Like Jessie Renton likes this

Great thank you @Tanguy Crusson - much appreciated and the video was super helpful :D 

@Tanguy Crusson Watched the video, thank you for that!

I am unable to see the Edit Field view on User Feedback Impact and Priority Score.  Are these fields and the algorithm behind them only controlled by the application?  If so, that is fine.

Can you provide how the User Feedback Impact and Priority Score are calculated?  Like just what fields and what percentages.  I understand the normalization from your video.

@Erin Mihalik it sounds like you're not a project administrator. You'll need to ask the project admin to add you to this role in Project settings > Access

Screen Shot 2021-05-28 at 10.40.00 AM.png

This will let you both see how the fields are configured and change that configuration. Let me know if you have issues finding how to do that!

Oooh never mind sorry, I think you faced a bug we had yesterday, and fixed since then!

let me know if it still doesn't work for you - it should be fixed now

Also, we've added a quick guide here that explains how that field is configured: Screen Shot 2021-05-28 at 10.47.42 AM.png

Comment

Log in or Sign up to comment
TAGS

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you