Hello community,
I have a further challenge with JPD, automation/JQL and "Autofill" dates.
It appears that any "Autofill" date is only visible from within views created in the JPD project.
If I write a JQL and show a column that is an "autofill" defined field, it shows blank in the JQL. Similarly, if I capture the smart value of the "autofill" field from within JIRA automation it is also blank.
Has anyone else experienced this? If so, have you found a solution/work around?
I am just wondering if this is the same scenario as calculated fields in JPD - Is this a limitation of the "autofill" dates fields? In that you can only see the field contents from within a JPD project view?
We really wanted to be able to extract these rollup dates in our filter queries and also make decisions in automations based on their contents/values.
Okay, thank you Tanguy. I would be great to have these soonest, happy to vote for them