incomplete epic showing green in program board

manish a October 31, 2023

Hi

in the program board the epic is showing as green however the stories within the epic are not completed and even the epic is not completed. then why is it showing in green.

 

green but epic not completed.png

3 answers

1 accepted

0 votes
Answer accepted
Jamie Giantonio
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
October 31, 2023

@manish a that feature looks like it is associated to 2 teams. The Falcons work is accepted and that is why that feature is green in that row. You should see that feature under the VIH teams row as well. Since that work is NOT done, i would expect that instance of this feature will not be green. Please let me know if that helps

0 votes
manish a October 31, 2023

Thanks Jamie. Understood its team wise. 

0 votes
Allan Maxwell
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
October 31, 2023

It is perfectly acceptable and perhaps desirable for the Product Team to "accept" a Feature without all (or any) of the Stories being completed.  What you see is the expected behavior.  In the example below, neither Team has even started their Stories but the Feature is green for both as per the PO accepting the Feature as is.  Perhaps they discovered a way to enable the functionality without completing any of these Stories.

 

Screenshot 2023-10-31 at 8.30.43 AM.png