Is there a report that shows the estimated story points and actual LOE?

Rebecca Hylek May 16, 2023

In an effort to help our business leaders have a better understanding of the work effort to complete features, we would like to look at our T-shirt estimation conversions compared to the actual level of effort for planned work.  Our goal is to see if there are any trends in our historical data to support a revision of our T-shirt estimation conversion chart.

Is there a report in Jira Align that will show both?  For example, with the feature below, the T-shirt size should have been Medium because the LOE was more than double the work effort and it took more time and resources than expected.

Feature:

FORD-1234

T-shirt size X-Small

  • Estimation Conversion
    • 12 Member Weeks
    • 2 Team Weeks
    • 3 FTE/mo
    • 18 Story Points

Actual Story Points (LOE) to complete the feature = 38

1 answer

3 votes
Jennelle Stearns
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
May 16, 2023

@Rebecca Hylek You could go to the features grid in Jira Align (Program-Features), and then add the columns T-Shirt, Points (This is the Feature points using the conversion table to convert your t-shirt size to points), and Story Points (this is the sum of the LOE's from the stories).

 