in jira align program room i can see sprint 215: 131 out of 135 stories complete. How to know the stories which were actually missed.
@manish a one way you could do it is to go to the Stories Grid (not backlog) (New Nav - Items -> Stories, filter by the Program and the increment (same as what you are using for Program Room) and State not= Accepted. Select More Actions and export the stories. Then filter on the column called Sync Sprint (select Sprint 215). That should show you the stories in that sync/anchor sprint that weren't completed.
Great. This helps.
however if sync sprint filter option was available in the grid view itself then it would have been much much easier.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
one follow up questions. if in jira they have moved the story to subsequent sprint post that sprint start. will it also get counted here.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
@manish The work in progress report (team level reports) will also provide you detailed info on stories