Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in

Can we create Risk at Multi Program Level?

Rupinder Pannu
Contributor
June 5, 2022

Hi All,

Is there a way to create RISK at Multi-Program Level for tracking, transparency & visibility?

We tried to raise a RISK at Feature Level which has multi-programs tagged but could only see the RISK under Primary Tagged Program only not the other additional programs.

What would you advice?

Best Regards,

Rupinder

1 answer

1 accepted

0 votes
Answer accepted
Allan Maxwell
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
June 5, 2022

I do not see away to have a multiprogram risk.  I guess you could make it a Portfolio risk or duplicate the risk for each Program.

Rupinder Pannu
Contributor
June 6, 2022

Thank You Allan :)

Suggest an answer

Log in or Sign up to answer
TAGS
AUG Leaders

Atlassian Community Events