Close Crucible review with too many files

We had a massive change to the look of our website that included over 19,000 files that where committed. When one of our users created a review for that changeset, it slowed Crucible to a crawl. We can't open the close the review because it's too large and I suspect Crucible is still working to add all the files to the review. I get a 502.3 Bad Gateway error...operation timed out. Is there a way to close or delete the review before it finishes adding all the files?

1 answer

1 accepted

Accepted Answer
0 votes

We tried re-starting the Crucible windows service. It seemed to take a few minutes to re-start, but that seemed to do the trick. Now we are going to try another way to add the files.

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Monday in Jira Ops

Jira Ops Early Access Program Update #1: Announcing our next feature and a new integration

Thanks for signing up for Jira Ops! I’m Matt Ryall, leader for the Jira Ops product team at Atlassian. Since this is a brand new product, we’ll be delivering improvements quickly and sharing updates...

324 views 0 8
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you