Hi guys!
I would like to start a discussion on the market standard (if there is one) for user inactivation during vacation.
Our users are marked as inactive when they enter their vacation time and then marked as active when they come back to the company.
The issue is: Portfolio for Jira users disappear from the Plan as soon as they are marked inactive.
In this scenario, activities that were assigned for them (even for dates after the user is back) are distributed to other users. Also, it is not possible to assign new issues for the users to work when they get back to work and it is not possible to add them to a Team (while setting up Portfolio for Jira for a new team).
Do you guys face a similar problem? How do you deal with that?
Thank you very much!
Cris
Hi Nic! How are you doing?
This process is done by another team in our company.
I will try to talk to them in order to change this process.
Thank you very much for giving me your point of view.
Cris