Table of contents and Dynamic TaskList

Matt Parker January 17, 2012

This is running Confluence 4.1.2. I have a template that I am using that contains a table of contents as well as a tasklist. Whenever the tasklist comes after the table of contents I cannot add items to the tasklist. If I remove the TOC or put the tasklist first everything works as expected. If I create the tasklist and have it before the TOC and then add task items everything is great. If I then copy that tasklist and copy it below the TOC none of the previously entered task items show up and I cannot add new items.

Any thoughts on why this problem is happening? I even tried excluding the tasklist from the filter but it still does not work.

Thanks,

Matt

1 answer

1 accepted

0 votes
Answer accepted
Joe Clark
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
January 17, 2012

It appears to be a known bug: https://jira.atlassian.com/browse/CONF-16181

Matt Parker January 18, 2012

Thanks, I will remember to check out the bug listings next time.

Matt Parker January 18, 2012

Looks like it has been on the list for over 2 years. I don't expect this to be fixed anytime soon.