You're on your way to the next level! Join the Kudos program to earn points and save your progress.
Level 1: Seed
25 / 150 points
Next: Root
1 badge earned
Challenges come and go, but your rewards stay with you. Do more to earn more!
What goes around comes around! Share the love by gifting kudos to your peers.
Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!
Join now to unlock these features and more
The Atlassian Community can help you and your team get more value out of Atlassian products and practices.
Help set up automation of the start date and end date of the task, so that when you start working with the task, the date is set automatically in the start date field and when the task is closed, the date the task is closed is set.
I'm still new to Jira and therefore I still don't understand everything well, I need your help.
When you start working on the task, let us say by clicking workflow transition button (Start Progress or something similar) then that is already stored in Jira. Similarly for end date. Also there is a Resolution date.
Yes you can automate to capture these dates and update custom fields. In your automation rule you can use transition trigger and update your date fields using smartvalue {{now}}, but I don't think it is necessary because the dates are already there in Jira which you can fetch and report on.
I hope it helps.
Ravi
СThanks, it helped me a lot, but I can't re-add the task state trigger. Can you suggest how to do it?