Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,466,312
Community Members
 
Community Events
176
Community Groups

View work log at JIRA - Feature Level

Edited

Hi ,

We have additional  levels of hierarchy in our JIRA , project->feature->epic->story->sub task. We logged hours for stories and sub tasks

 Is it possible to show / Display the sum of logged hours on Feature level ?

2 answers

1 accepted

0 votes
Answer accepted

Hi @Shashikant Mahadik 

Not out of the box, you can either build automation to roll up numbers to above level. It may not be straight forward but possible.

I normally rely on eazyBI to build a report to show progress at higher levels. If you are already using Advanced Roadmaps then eazyBI can use that hierarchy to show you this roll up number at any level.

Ravi

Thank you @Ravi Sagar _Sparxsys_  

I will try eazyBI.  :-)

0 votes
Rahul_RVS_Support Marketplace Partner Jul 21, 2022

Hi @Shashikant Mahadik 

Welcome to the community !!

If you are fine with a mktplace app, you can have a look at our add-on to get this data -

Issue Hierarchy Reports 

and generate insights such as:

- View the full Jira Issue Type hierarchy of Linked issues,
Portfolio/Advanced Roadmaps, Epics, and Subtasks up to 10 levels.

- % complete based on time spent and story points at each hierarchy level

- Sum up Time Spent, Org Estimate, Time Rmng, custom number
fields

 

Links HIerarchy.PNG