Hi, 

is it possible to add the year to the milestone date we have on the Gantt in Jira structure? 

for example in the picture below the due date for the milestone is December 31, 2022

but the milestone shows only 31/12. 

the due date field shows the full date.

image.png

1 answer

Suggest an answer

Log in or Sign up to answer
0 votes
Stepan Kholodov _Tempo_
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
September 2, 2024

Hello @Mor 

The year can't be displayed on the chart; however, you can add the Gantt Milestone Date column to your structure and see the date there. You can also use the Formula column for adding more visibility to certain milestones, depending on their year/date/other attributes.

I hope this helps. If you have more questions about Structure, please reach out to us directly at our support portal.

Best regards,
Stepan