Hi,
I'm new here and I don't know if I am in the right chat. But we use the PI Roadmap in Jira in our project and regularly take a look at the dependency bubbles in the roadmap.
Among other use cases a dependency bubble turns red if the lead time of two issues with a "has to be started together"-dependency is different.
I don't know the idea of the lead time but we usually create an issue during a running PI and plan the implementation in the next PI planning. So the lead time is not necessary for our plans which is why I wanted to ask:
Is there a possibility to deactivate the automatic consideration of the lead time for the evaluation of a dependency risk?
In the PI roadmap scheduling settings for dependencies I can only choose between concurrent or sequential scheduling and I already chose concurrent but the dependency bubble is still red because of the different lead time...
If the deactivation is not possible, yet is it planned? I couldn't find it on my search.
Thank you very much in advance for your help.