Back in the Portfolio for Jira days we used to be able to set default estimates for un-estimated work items in the live plan.
This worked out great because all I did was take the cycle time from the control chart of the board issue source and plug that into the default estimate. This gave us a reasonably accurate view of when we could get stuff implemented for kanban teams.
I don't see this feature anywhere in the new view.
Am I missing something?