Is it safe to delete a test plan in portfolio plan for jira?

Shawn Matthews June 27, 2019

I've been testing portfolio plan, but want to delete my test plan. My jira data is safe, right?!??!?

1 answer

1 accepted

0 votes
Answer accepted
Earl McCutcheon
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
July 1, 2019

Hi Shawn,

You can delete the plan without worry, the Jira issue data is not going to be altered by the removal of the plan.  

Portfolio pulls the data sources from the jira issue and commits the data back to Jira on approval so when a plan is deleted only the portfolio specific data, or data that has not been committed is affected from the issue, exe the team field will be removed, or any changes to the data on the plan that has not yet been committed/saved.

When recreating a plan it will repopulate the data as you modify the plan and commit new values.

Regards,
Earl

Shawn Matthews July 8, 2019

Thanks Earl!