I'm currently working on planning out future work. I expect the work to take 5 sprints, but have not yet created detailed user stories in Jira. I entered a ticket that has story points of 5x the team velocity. If I go to View Settings, View by Team, and select show capacity on time-line. It appears that the Assigned Sprint turns Red (>400%), but the following sprints are at 0%. If I remove the assigned sprint from the ticket, then capacity shows 0% full despite the task bar and team assignment.
How do I show the team capacity during those sprints in portfolio?