Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Holiday scheme in Portfolio for JIRA

Hi,

I am currently responsible for Atlassian tools in a software organization of around 1000 users, and am concentrating on moving from using Tempo to Portfolio.

In Tempo, there is something called "Holiday Scheme", and since we are not international, we pre-defined our national holiday scheme and it has been inherited for every team created.

After researching Portfolio for JIRA, I only saw options to define "exceptions" for specific person, team of plan, but only in a manual manner. Is there a way to define a holiday scheme, or to define exceptions globally (for the entire JIRA instance)?

 

Thanks.

2 answers

1 accepted

1 vote
Answer accepted
Rhys Christian
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
Aug 07, 2017

Hi Avishay,

Unfortunately holidays cannot be set at a global level for the entire instance.The highest level you can set such exceptions is at a plan level. In your plan go to the configuration > Working hours and days.

From here you can set the Non-working days which will apply for everyone in that plan.

Cheers,

Rhys

Thank you Rhys. I wonder whether there is a way to write a script to go over all existing plans and perform the same operations (which yield the creation of some non-working days) for each plan.

Like Amin Pazhohesh likes this


Hi Rhys,

Is there any Atlassian ticket reported to this issue? Is it intended to be changed?

Thanks in advance,
Balázs

Suggest an answer

Log in or Sign up to answer
TAGS
AUG Leaders

Atlassian Community Events