I have created the future sprints in preparation for our PI planning but in our sprint capacity management view, I am unable to see the specific sprints that I created. All I can see is the projected sprint. I have already configured my issue source.
Ty!
This is most likely linked to the way you have configured issue sources of your plan. Sprints are a feature of a scrum board, and they would normally be loaded into your plan automatically when you choose a board as an issue source.
Check your plan settings / issue sources and verify how you are now pulling in issues into your plan. My guess is that you may be using either projects or filters there as the source(s). Replace those with your actual board(s) where your sprint was created and that should fix this.
Hope this helps!!
Thanks @Mohammed Aamer Khan for your reply. I actually have the board already indicated as an issue source. And I can see the future sprints that I created in the dropdown.
What is weird also is the current sprint is showing exactly as it but the future sprints aren't