[Data Center] Question regarding Kanban team capacity in Advanced Roadmap

Duc Thang TRAN March 14, 2024

Hello,

do you know how Advanced Roadmap splits time for a Kanban team capacity?

For example, I have a  Kanban team  with 185 hours per week and 5 members.

I have 2 issues with start dates on April 1st, 2024, and April 30th, 2024, with a total original estimated duration of 268 hours.

I expected my team's capacity to be 53.6/185 hours per week for 5 weeks (flat mode).

But I got these values 74/60/37/37/60 for these 5 weeks.

Do you know how this capacity is calculated?

Do I have the possibility to set it as flat mode, front-loaded, back-loaded, or distribute hours manually per week?

 

Best,

2024-03-14 14_08_20-Window.png

0 answers