Are you in the loop? Keep up with the latest by making sure you're subscribed to Community Announcements. Just click Watch and select Articles.

×
Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Capacity and Planning: Tasks Estimated for week (h) 8 + 8 + 8 + 8 + 10 = 32h for week, why?

Hi everyone!

Pretty sure that it is a really simple question and I'm still evaluating Portfolio mainly for release planning and capacity overview, I do struggle with one weird behaviour I get:

  • 5 tasks planned for 1 developer for 1 week:
  • 4 task for 8h (FT)
  • 1 task for 10h

When calculating Portfolio shows me a 32h capacity used for the defined week and it moved that 10h task for the next week.

Question: why I can't have him work on, let's say, Friday for 8h and resume on Monday next week with the leftover of 2h?

Many thanks for help!

1 answer

1 vote
somethingblue
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
Jan 25, 2018 • edited

Hi Mirek,

There is a Suggestion that may help understand this behavior at Allow portfolio to book stories into sprints if any capacity is available.

The logic is the Full capacity need to be available and the velocity is 40h for the user and the 8+8+8+8+10=42 so one full issue pushed, but a way to get more out of this is the priority arrangement as covered in Scheduling behavior:

The scheduling algorithm currently optimizes the scheduling of highest priority items first. Even if there might be a scenario where the team could fit in a bit more capacity into a release if it started with a lower priority item,  Portfolio for Jira  will not suggest this in the schedule. Items that have the highest priority should also be started first. Also, you might want to prioritize items with the highest risk first to tackle uncertainty early in the process.

See if this works for you:

 

Break the 10 into two issues as an 8 and a 2 hour and prioritize the 8 hour portion above the 2 hour portion. The 2 hour portion will be moved and the 8 will fill capacity.

 

Example: 8 hours scheduled on the main issue and 2 hours scheduled to a second issue set for Follow up on issue 1

Take a look at JPOSERVER-1867 and if you believe that fits this scenario please vote on it and add your use case to the comments. Let me know if that helps. 

Cheers,

Branden

Suggest an answer

Log in or Sign up to answer
TAGS
AUG Leaders

Atlassian Community Events