Hola a todos!
alguien ha encontrado alguna forma o apps, que permita calcular el porcentaje de avance real de un proyecto (para todo el proyecto), vs el porcentaje esperado?
He tratado con Big Picture y Road Maps, y no he encontrado solución a mi necesidad.
Saludos,/
Hi @Marcin Geb _SoftwarePlant_
Thanks for your clarification.
Does expected progress works in Big Picture 8?
I can't find any documentation that helps me to calculate this progress correctly. according to the attached picture, this progress calculated equal to 100% for all issues in my plan. Could you help me with that?
Hi @Ansar Rezaei ,
Expected progress in BigPicture 8 does not work at the moment. We are sorry for the inconvenience. However, we are continuously working on BigPicture improvement, and we are aware that our clients need this functionality.
We plan to add a new feature: Expected Progress displayed in the column as a lozenge (like Time Tracking columns).
You can follow work progress in the feature request ticket: ONE-28625. Please note that it is best to open it in the incognito tab of your browser.
Best,
Anna
SoftwarePlant Support
Thanks for your clarification.
Do you have any estimate about when you deliver it?
Hello @Ansar Rezaei
I am really happy that you find my answer useful.
There is no ETA for this feature yet. There are many requests in our backlog, and some of them do have a very high priority at the moment. However, I recommend following the request status and its Customer Rank.
Best,
Anna
SoftwarePlant Support