Hi, I would like for the end date of a sprint to determine the due date of an issue. So if I assign a given sprint to an issue, the due date of that issue becomes the end date of the sprint.
The farthest sprint end date of all the issues in an Epic should determine the due date of the Epic and be visualized on my roadmap.
Any tips on how to achieve these things are greatly appreciated!
Thank you
Welcome to the Atlassian Community
For your first paragraph, simply configure the plan as below.
i.e. have Due Date as the end date for the plan and make sure the tickbox is ticked to enable sprint dates when issues don't have dates.
For the 2nd paragraph, you would need to do some form of automation to achieve that.
Hello Atlassian Community! Feedback from customers like you has helped us shape and improve Jira Software. As Head of Product, Jira Software, I wanted to take this opportunity to share an update on...
Connect with like-minded Atlassian users at free events near you!
Find an eventConnect with like-minded Atlassian users at free events near you!
Unfortunately there are no Community Events near you at the moment.
Host an eventYou're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.