Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in

Can we use skills without stages?

Jeroen Thoelen March 26, 2018

Hi, 

In our portfolio plan we configured several skills ( like team lead, developer, architect etc. ), but do we need to configure stages as well for using it properly, or can we use skills without stages? 

Thank you!

1 answer

0 votes
JamieGeorgeson
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
April 27, 2018

Hi Jeroen,

Yes - you are able to use Skills without Stages.

You can break down an estimation for an issue by skill (e.g. 25% architect, 75% development). You can assign Skills to Team Members in a Plan, and Portfolio will schedule issues according to the availability of skills in the team. This can by useful for finding bottlenecks in planning introduced by work items requiring specialised experience.

Stages are more about capturing sequential activities within a work item (e.g. a design stage followed by implementation).

Thanks,

The Portfolio for Jira team.

Suggest an answer

Log in or Sign up to answer
TAGS
AUG Leaders

Atlassian Community Events