I cannot find a way to group tasks into Epics using Agility. It is clearly documented for Scrum and Kanban boards, but doesn't appear in documentation for agility. Is this feature missing?
Hello Matthew,
Are you trying to group the tasks per Epic in the backlog view or in the Active Sprint/board view?
There are two features that may help you to achieve the functionality you are looking for.
In the Active Sprint/board:
You can configure your swimlanes to be grouped by Epic. You just need to navigate to your board > click in the three dots icon (...) > Board Settings > Swimlanes
For Backlog view:
You can add the parameter order by "Epic Link" to your filter query.
I'm looking at the Board view (I've turned off the Sprint feature on this board, but enabled the Backlog feature). The only options in the three dots is "Manage Rule".
The three dots menu I'm talking about is the one in the top-right corner of the screen:
Is this the same menu you are referring to? Can you please provide us a screenshot of your board?
Hi,
Here is the image showing the three dots menu options.
Thanks
It seems that you created your project with the Agility template. This template was developed for the customers which do not need any kind of customizations, providing only the simple view of project boards.
If you want to perform more customizations on JIRA as the ones I mentioned before, you will need to start a new project using a Scrum or Kanban template.