Hello,
We are using automation to generate epics -> stories -> sub-tasks. This is being used to create a list for an onboarding of a new product for our clients. Sometimes we have a delay and this causes an inconsistency in the due-dates. We need to postpone the due-dates of around 60% of the sub-tasks. I have tried to used bulk-edit, but there you can only change the due-date to a specific date, not 2weeks in the future. Any ideas how can we perform this action?
Maybe few more details about our version, we are using Jira Data Center at the moment. As for the automation once, the user creates an epic with the special field selection, the automation will be triggered. We usually have the structure of an EPIC -> Stories (around 6) -> Sub-Task (each story has around 10-20 sub-tasks).