In the backlog, where we can show the estimations for tasks, original estimations for 'In progress' & 'Done' tasks is correct, but for "To Do" it is showing zero, although I have many tickets with in "To Do" status with original estimates added.
Hello @Aleena Umaiir
Can you show us the mapping of Statuses to Columns in your board view?
I recall that there was some limitation to how the gray lozenge summarizes information. I'm looking for that information. As soon as I find it, I'll add another response.
Hi @Aleena Umaiir , can you share a screenshot of where you are observing this?
Here in the backlog , I have an item in 'To do' with 1d estimation, but it is showing 0.
this is happening in only this project
@Jack Brickey can you please help me in this? I am stuck here
It should show the estimates of "To Do" items, it is showing me 0
I found the reference. While it talks about story points it might also apply to time estimates.
Check if this description matches your experience.
https://confluence.atlassian.com/jirakb/estimation-of-story-points-observed-on-the-backlog-does-not-match-the-status-category-1381826620.html
It actually helped @Trudy P Claspill , my leftmost column has no status assigned and it was not TO Do, I removed that, and now my leftmost is TO DO, with its respective status and it's showing the estimations.
Thanks again!
I'm glad I could help you.
If my response helped you solve your problem please consider clicking on the Accept Answer button to mark you post as Solved.
Hi @Aleena Umaiir , sorry for not getting back to you. I disappeared on vacation. I have deselected my response as "accepted" as it was incomplete and did not provide the answer. I have selected Trudy's answer as accepted as I believe it accurately presents the solution. If you feel otherwise please deselect and let us know.
It looks like you're new here. Sign in or register to get started.