helo everyone, i have problem with jira report. i estimate for task in sprint. but when i running sprint, i can't see a burndown report. please help me urgent !
@Fabio Racobaldo _Catworkx_ could you help me?
Welcome to the Atlassian Community!
Assuming it is a Company-managed scrum or kanban
1> we using subtask, it not working for burndown and burnup chart, right?2> we will hide task when done in last column, it mean all task in close sprint will not show in active sprint. so velocity can't show it, right?
1. Burndown is a function of sprints. Sub tasks (in Jira) are part of a story, not sprint items. So sprint estimation on sub tasks is nonsense. Do not do it (other estimation is fine, just not sprint/scrum)
2. If you hide it, then by definition, you cannot report on it.
thank you so much!
Best wishes,Long