I'd like to set the 1-week sprints for my project and then modify the start end dates for each - how do I do this, please?
Hello Parag,
Thank you for getting in touch with Atlassian Community!You can change the start and end date of a sprint through the backlog.Please, go to the backlog and on the ... click on "Edit sprint", change the dates and click on "Update".
Hope this helps!
Regards,Angélica
Thanks but when I click on 'Edit Sprint' I get the attached:
Hi Parag,
Thank you for the details.Are you using Next-Gen or Classic project?Are you the only user facing this issue?Was there any change before this issue happens?