I want to use card colors to show which cards have been moved to DONE during this (ongoing) week.
But how can I make a query for "status changed to DONE during this week"?
This is my query for green now:
project = "Super Buddies Kanban" AND updatedDate > startOfWeek(0d) AND status = Done
I realize that with this query cards are green also if they are in status DONE and had just an update of any kind this week, but were moved to DONE much earlier than this week, i.e. not moved to DONE during this week :-(.
I want to get rid of this faulty coloring.
Thanks in advance!