Hi Guys,
My sprint starts in 2 days (31.10) and I want to start it with that date.
Currenly NO running sprints.
When I access the start sprint box, I fill in the info and then no "Start" button.
I see this message: Issues SP-125, SP-111, SP-110, SP-108 and 4 others do not have a value for the 'Remaining' field. Values entered after the start of the sprint will be treated as scope change
Notice: the team creates sub-tasks under each user story, and within the sub-task we have the original estimate (can the US calculate the estimate automatically?)
How can I start the sprint?
Thanks,
Eran