Hi
We use the status "Rejected" for tickets and during a sprint and item might be transitioned into this status. These are not being reflected meaningfully in the sprint burn down and sprint reports.
Board settings:
1) Place the "Rejected" status into the Done, far right column, on a scrum board. Complete print. The ticket appears as completed and its value is added to the completed tasks story points, which falsely increases the story point value done.
2) Place "Rejected" on the board in its own "Rejected column" or another existing column. Complete sprint. The Rejected ticket gets handled with all other incomplete tickets and will be sent to the backlog of my choice and remain active, which is also not desired.
Any ideas how to handle these rejected tickets?
BTW, resolution is set to "Declined"