Hello,
I would like to be able to change the "issue added to sprint" date.
I often create the sprints after they are started (I know that it's not the correct agile process but sometimes I can't do anyway else).
For example, I often do the following process:
- create some tickets
- estimate them
- log work (giving a date in the past)
- create sprint (start date in the past, end date in the future)
- add tickets to the sprint
- start sprint
=> The reports are unusable (burndown, burnup and sprint reports) because the date the tickets are added to the sprint are after the date they were estimated. Estimation is then not taken in account. Neither the time spent.
Is there a way to change this date?
Best regards,