The question is - how does Control Chart works in details.
Preconditions - for instance we have Kanban dashboard with 3 columns - Open, In Progress, In Testing.
we have following configuration for Control Chart
Timeframe: June 1 till June 7
Columns: Open
Filters: NONE
Let's say we have following issues (tickets):
#1 Created on May 1st (appeared in Open column), moved to "In progress" on June 2nd, resolved on June 6
#2 Created on May 1st (appeared in Open column), moved to "In progress" on June 2nd, resolved on June 10
#3 Created on June 2nd (appeared in Open column), moved to "In progress" on June 2nd, resolved on June 6
#4 Created on June 2nd (appeared in Open column), moved to "In progress" on June 2nd, resolved on June 10
Which of this Issues will be displayed on Control Chart?
Which of this Issues will be included in calculation for items above the chart: average, median, min time, max time, issues ?
What changes if I add one more column to the Chart configuration (Columns: Open, In progress) ?