I have just taken up a project as Scrum Master and I am seeing that all the previous sprints have been kept open and not marked as Closed/Completed.
I am not sure what the reason is but this seems wrong to me. The velocity chart is not getting reflected since sprints are not marked as closed or completed.
Can anyone please help me in understanding what all will be the impacts or any other places where I will see impact because of this in case the Sprint is kept open. Are any of the charts/reports impacted due to this?