Hello There,
I have an issue being faced for which I require experts to throw some light on my doubt.
We have a Scrum team comprising a 1 UI designer, Developer, 2 PHP and a Tester working on a project.
We have the tasks identified for the sprint and ready to start with and created sub tasks for each story separately for UI design, Development, PHP service and testing.
The problem is there are few tasks where the UI Developer cannot contribute for this sprint which was taken by the PHP guys. The challenge for me is how to assign those sub tasks to the sprint and get a track of the PHP guys alone, because when i assign the story it includes the other sub tasks (UI design and Development) and its estimation as well. And when i try assigning the Sub task alone its not reflecting as its related to a Parent story.
Please suggest me some steps to get this solved. Looking forward for your answers.
Thanks,
Sathish