I want the burnup / down standard reports to report "complete" from a different column of the sprint workflow rather than the last one. Does anyone know how i can change this setting? Thanks!
In Agile, you burn down on "done". Jira Software defines this as "the last column on the board". There is no way to use other columns.
thanks! Our team are currently only moving to done after the product demo / sprint review which renders the reporting useless until the end of the sprint. Looks like we need to change the definition of done.
You could add a Closed status following Done and use closed post sprint review. Then change process to move to done when work is done.
thanks for the advise. I'll look into doing this so we can track our progress through the sprint