My sprint burndown chart does not show the red line (remaining effort) . until last sprint the line was drawn....can you help me?
Hi Natalia
Make sure that your board has 'time tracking' set to "Remaining Estimate and Time spent" in the Estimate tab of the board's configure section.
It looks like you're new here. Sign in or register to get started.