I am currently tracking a version in JIRA.
The current status is that 28 story points have yet to be completed. Team average velocity should be around 29 story points per sprint, and each sprint has a duration of 2 weeks. I would expect a projected end date of ~2 weeks, but I see that the version reports indicate the versions to be ready in ~2 months from now.
Am I missing something? Is the version report taking into account something I do not see (e.g. the rate with which new issues are created in the same version)?