I am trying to find out if there is a way to run a report in JIRA to show items that were added after the start of the sprint. This is so we can determine how much sprint creep we are encountering.
Thanks
Hi Will,
You can use the Burndown Chart report to see this information. That report will track items added to a sprint after the sprint has started as a scope change.
Regards,Andy