Fresh installation; new project; new portfolio plan.
I have 5 developers, some are frontend, some are backend. Some stories need one skill, some stories need both. I think I've associated the team correctly with their skills;
I think I've properly identified on each story how many days are needed for frontend and backend.
I have also organized the epics in priority order, along with the stories under them.
When I schedule, some stories have an error that "Scheduling not possible due to skill gaps." But the task right below it (which should be prioritized/scheduled first) doesn't have that issue.
What am I doing wrong?