When should you create a subtask? It seems like a simple question but I can't find the answer anywhere. Should it be before the sprint starts or after it's started?
Note the following if the subtask is created before the sprint starts:
1) Subtasks are NOT visible on the product backlog.
2) Subtask estimates are NOT not included in the total 'Estimate' field for all issues on the product backlog.
3) Subtask estimates ARE included in the 'Remaining' estimate field for all issues on the product backlog.
4) When filtering on a user, the total 'Remaining' includes the remaining estimate of a subtask if the parent task is assigned to that user, even if the subtask is assigned to a different user.
If a subtask is created once the sprint starts, doesn't that affect sprint scope?