Hello, I am using the structure "Epic -> Story -> Sub-Task" to manage the development. There are a few Tasks that the team is converting to Sub-Tasks, they will disapear.
So, I went to Backlog screen and clicked on the "Only Tasks and Sub-Tasks" filter. It is showing me only the Tasks!! The Sub-Tasks are not being showed:

The only way to see the Sub-Tasks is through Search screen:

Is it possible to show the Sub-Tasks on the Backlog screen? There is any configuration that must be made, or field to fill?
Thank you