I am using JIRA 5.0.4 and Greenhopper 5.9.6. We are experiencing issues with the Time Remaining summary in Greenhopper. I have a case open with Atlassian.
I am being told by Atlassian that the reason this is occuring is because we edit the time remaining for issues. They are saying we should not edit that. THey are also saying that Greenhopper calculates the time remaining as original estimate - time spent.
Am I missing something? I thought the whole purpose of the time remaining field is to allow users to change it when they find out the work remaining is different than the original estimate - time spent.
Thanks.