Hi all,
Been scanning the forums and tried all of the fixes but still cannot see issues in our backlog. I've double checked against another project we have going and can't see any difference in the set up. This is for JIRA Cloud.
Glad to be wrong here but I think my set up is correct. Screenshot is of my column assignment:
My filter query is: project = PMO ORDER BY Rank ASC
As you can see by the screenshot, there should be 54 incomplete tasks (TODO + InProgress), I have confirmed this doing a general search for issues. When I check the Scrum board, the active sprint + backlog only yields 29 issues.
I have tried re-indexing and it doesn't seem to fix the problem.