If I go to the velocity chart for a completed sprint, GH shows that the committed is say 13, completed is say 11
But when I go to the sprint report it shows me that the completed stories story points = 6 even though some of them are closed won't fix and hence shouldn't be counted.
so I have 2 questions:
1) why does the completed story point count != the velocity chart? It appears that the velocity chart is counting story points for tickets that were removed from the sprint (they're in the removed from sprint section ) and completed in the following sprint
2) it is counting the state of Closed Won't Fix. We shouldn't be counting these as they essentially ended up being no work. How do I tell GH not to count Closed?