Hi
We use jira-agile with scrum boards and sprints.
What we want is to in some way find a sum of the remaining estimate by column.
e.g. We have a column Open , In Development and In Test, i want to find out total what is remaining estimate for all issues that are in Open column and so on...
I know out of box we cant achieve it; is there a workaround to get this information?
This information will inform us which column is becoming the bottleneck in the current sprint.
Rahul