We are using Portfolio to plan a combined software and hardware project, where there will be substantial ordering and prototype manufacturing delays as part of some of the workstreams. While these workstreams are delayed, the teams that were busy specifying components and preparing design documents can work on other things and then return to work on the higher-priority project once the parts come in.
I can 'hack' Portfolio to model this behaviour by making a 40hr/week resource called 'Ship' or 'Manufacturing Contractor' and then setup dependencies appropriately, but this doesn't easily scale (for example, one would need two 'Ship' resources to model the shipment of two independent major components that were ordered at about the same time but had different lead times).
Is there a way we can make a work item that takes a fixed period of time but requires no resources?